This is not your grandfather’s heavy timber structure

Posted on August 17, 2012

The following post is by Brad Kahn:

The last few months have been busy at the Bullitt Center construction site on Madison Street, with structural, glazing, mechanical and other systems taking shape.

Photo by John Stamets

Glaziers install windows on the sixth floor.

The Type-4 heavy timber structure is a first for Seattle since the 1920's, when heavy timbers were used in most commercial buildings. In the interim, the technology of heavy timber structures has advanced, with glued-laminated timbers replacing solid wood in many cases. Of course, forestry practices have also improved in the last 90 years, with 100% of the wood used at the Bullitt Center coming from Forest Stewardship Council certified forests.

At this point, the structural work at the Bullitt Center – designed for a 250-year lifespan – is largely complete, with the roof firmly in place.

With the structure complete, work turned to the curtain wall. Of particular note, the Schuco window system being used is arguably the most efficient in the world. Yet before the Bullitt Center, these windows were not easily available on the West Coast, since the manufacturer was in Germany – quite a distance to ship windows weighing hundreds of pounds each. To address this challenge, the team was able to connect Schuco with Goldfinch Brothers, a glazing company in Everett, WA. Now Goldfinch is the exclusive manufacturer of the Schuco window system on the West coast, providing windows for the Bullitt Center and other projects.

Photo by John Stamets

A rainwater collection and treatment system is being built throughout the project.

On the mechanical side, the rainwater collection and treatment system is being built throughout the project, from roof to basement. While approval to use rainwater for drinking is pending, it is our hope that the Bullitt Center can help demonstrate that ultra-filtration, UV and activated charcoal can treat water as well as – if not better than – chlorine (which can't be use in the project, because chemicals are not allowed for water purification by the Living Building Challenge).

At this point, the Bullitt Center is on track for completion later this year, with occupancy by commercial tenants starting in January 2013. Conversations with potential tenants are underway, and interested companies should contact Point32, the project development partner, for more information.

Brad Kahn is president of Groundwork Strategies. He manages communications for the Bullitt Center project.

 

Share this:
Share this page via Email Share this page via Stumble Upon Share this page via Digg this Share this page via Facebook Share this page via Twitter
Comments (0) Trackbacks (0)

Sorry, the comment form is closed at this time.

Trackbacks are disabled.