homeWelcome, sign in or click here to subscribe.login
     


 

 

Construction


print  email to a friend  reprints add to mydjc  

October 21, 2014

STP starts digging Bertha's rescue pit

Photo from WSDOT/Ox Blue [enlarge]

WSDOT image

Seattle Tunnel Partners have started digging the pit that will be used to rescue Bertha, the tunnel boring machine stuck 60 feet below the surface near Pier 48.

A Deere 225D LC excavator began digging the 120-foot-deep, 80-foot-wide pit on Friday. STP says it will use more excavating equipment as work progresses. The machines will remove about 20,000 cubic yards of soil, some of it contaminated.

Contaminated soil will be hauled by truck or barge to an approved disposal site. STP will store clean soil and use it to fill the pit after tunneling resumes.

STP doesn't plan to excavate every day because other construction activities are competing for space near the pit.

Crews installed the circular pit's concrete piles over the summer.

STP is using dewatering wells in and around the pit to lower the groundwater, which will make it easier to excavate the pit and move in Bertha. Five dewatering wells are inside the pit, four are between the pit and a cut-off wall, and three are outside the pit.

STP will add several depressurization wells outside the pit to help balance pressure at the bottom of the pit, which is a layer of clay. One has been installed and three will be added when the excavation gets to the 40-foot mark. Engineers also will take measurements at that point.

A massive crane will be used to hoist pieces of Bertha to the surface for repair later this fall.

STP stopped tunneling last December after Bertha overheated. An investigation found the machine's bearing seals were compromised.

STP expects to resume tunneling in late March.




Email or user name:
Password:
 
Forgot password? Click here.