homeWelcome, sign in or click here to subscribe.login
     


 

 

Construction


print  email to a friend  reprints add to mydjc  

May 19, 2016

Bertha back at it, mines 2,000 feet

SEATTLE — Seattle Tunnel Partners resumed mining late Tuesday following a break for rest and routine maintenance.

Crews had been mining around the clock since April 29 to clear the viaduct, which was shut down for 10 days during that operation. WSDOT reopened the viaduct on May 8, but STP kept mining until last Friday.

As of Wednesday, the tunnel machine named Bertha had mined 2,008 feet of its 9,270-foot route and installed more than 300 concrete tunnel rings.

Bertha is approaching the Columbia Street on-ramp to the viaduct.

A WSDOT spokeswoman said engineers believe it is safe for traffic to use the on-ramp while Bertha tunnels below, so the on-ramp will remain open.




Email or user name:
Password:
 
Forgot password? Click here.