homeWelcome, sign in or click here to subscribe.login
     


 

 

Construction


print  email to a friend  reprints add to mydjc  

May 9, 2017

Public works: Renovations

Photo courtesy of WACA
More than 14,000 square yards of concrete panels on U.S. 195 were removed and replaced.

U.S. 195 PCCP rehab

Location: Spokane

Owner/developer: Washington State Department of Transportation

Team: Wm. Winkler Co., general and concrete contractor; Spokane Rock Products, ready-mix supplier

This Washington Department of Transportation project included rehabilitation of 8.8 miles of the two southbound lanes of U.S. 195 between East Excelsior Road and Interstate 90 in Spokane.

The original 8-inch prestressed concrete cylinder pipe (PCCP) was constructed in phases from 1953 to 1964 and was experiencing severe failures. Minimal maintenance and repair had been performed over the 50-plus years of service life.

Work included removal and replacement of 14,400 square yards of Portland cement concrete panels, including base reconstruction; 4,200 square yards of panel jacking with chemical grout; 112,900 square yards of Portland cement concrete pavement grinding; 214,600 linear feet of joint repair and reconstruction; 29,300 square yards of micro-milling bituminous paving; 2,900 square yards of asphalt shoulder reconstruction and 58,400 square yards of slurry seal; 128,200 linear feet of pavement marking; associated tasks and significant traffic control.

U.S. 195 is the main traffic corridor for southbound traffic from Spokane to Pullman, and it was essential to maintain one lane of traffic throughout the course of construction. The fast-track, 80-day working schedule required multiple phases and types of work to occur simultaneously.

Logistics of removing and transporting existing materials while importing new materials for reconstruction was difficult while maintaining high volumes of traffic through the project area. The topography of the roadway compounded access to and from the project location.

Existing asphalt patches were milled and removed from the concrete road. Approximately 3,250 cubic yards of high early strength concrete was utilized for PCCP panel replacement at numerous locations along the roadway.

Once panels were replaced and others chemically grouted to grade, the entire roadway was ground to strict compliance. Severe wheel-path ruts were ground smooth to adjacent surfaces. At the same time, 40.6 miles of pavement joints were reconstructed, including spall repair, cleaning, routing and resealing.

While some of the PCCP time-stamped from 1953 to 1964 were removed, approximately 88 percent of the existing PCCP was rehabilitated for additional service life well beyond the current 50-plus years of operation. This project is a testament to the sustainability of concrete pavements, exemplifying the advantage of life-cycle costs.





Other Stories:



Email or user name:
Password:
 
Forgot password? Click here.