[DJC]
# 10
[TOP]

Hudson Bay High School Addition & Modernization

Hudson Bay High School

Hudson Bay High School



Project description: Construction includes brick veneer, concrete floors and walls with a steel superstructure and steel wall framing. Construct 30,000 square foot addition to house the new commons, full service kitchen, and complete media spaces. Construct two separate 10,000 square foot additions to an existing 45,000 square foot classroom building. Completely renovate two classroom buildings, two science room additions, and convert the existing media center into a science building. Renovate 30,000 square foot of arts, music, choir, and athletic space. Re-roof the majority of the campus, convert the steam system to boiler heat, and install a new fire alarm system and voice-data systems. Construct 60,000 square foot courtyard area to act as an outside amphitheater.

Address: 1206 East Reserve Street, Vancouver, Washington

Original contract amount: $16,646,000

Start of construction: July 1997

Expected completion date: September 1998

Contractor: Slayden Construction, PO Box 625, Stayton, OR 97383, 503-769-1969, fax 503-769-4525

Architect: LSW Architects, PC, 2300 Main Street, Vancouver, WA 98660, 360-694-8571, fax 360-694-9510

Owner: Vancouver School District No. 37

Project participants: Robert Agard Construction; Lakeside; Cascadian; Masonry Services,Inc.; Fought & Co.; Eagle Roofing; Woodburn Masonry, Inc.; Pacific Hardware & Specialties; Crawford Roll-Lite Doors; Inland Glass Inc.; Pacific Construction Systems; Fintex; CSI Interior Contractors; Ferguson Commercial Coatings; Global Supply; Lemons Millwork; Thyssen (U.S.) Elevator; Hydro-Temp; Fire Systems West; Robert Lloyd Sheet Metal; Control Contractors, Inc.; Prairie Electrical.

Copyright © 1998 Seattle Daily Journal of Commerce.