Renton Stage 2 Liquid Stream Improvements
|
Renton Stage 2 Liquid Stream Improvements
|
Project description: Construct two new influent bar screens, grit handling structure modifications, including addition of three new rotary screw dewatering machines, new grit classifiers, and various structural, piping and electrical modifications.
Modify the south primary treatment structure, including adding new sludge collectors, new scum collectors, new scum pumps, and various structural, piping and electrical modifications. Extend the new mixed-liquor channel, and the return activated sludge (RAS) channel.
Construct secondary sedimentation pod No. 6, which includes four 100-foot-diameter secondary sedimentation tanks, eight new RAS pumps, and associated channels and effluent flow control facilities. Modify the chlorine building, including two new chlorine neutralizing scrubbers, standby chlorination facilities and new post chlorination equipment.
Work also includes all associated piping, valves, heating, ventilating and cooling systems, electrical power, instrumentation and control systems, connections to the existing plant and storm drainage systems, outside piping, grading, paving, and interior and exterior demolition.
Address: 1200 Monster Road S.W., Renton
Original contract amount: $14,694,772
Start of construction: Nov. 13, 1997
Expected completion date: Dec. 31, 1999
Contractor: IMCO General Construction, 4509 Guide Meridian, Bellingham, WA 98226, 360-671-3936
Design engineer: Brown & Caldwell, 999 Third Ave., Suite 500, Seattle, WA 98104-4001, 206-624-1000
Owner: King County Professional and Construction Services
Project participants: DDJ Construction Co. Inc.; Magna Construction Group; Rainier Steel; D.W. Close Company Inc.; McDowell Northwest Inc.