Multi-Berth Wharf Facility, Port of Tacoma

Hyundai Terminal Wharf

Hyundai Merchant Marine Terminal Wharf



Project description: Construct a multiple-berth wharf facility on the Blair Waterway. Work consists of building a 121-by-2,000-foot pile-supported wharf. The concrete support piling will be provided by the Port of Tacoma. The wharf will be constructed adjacent to an existing wharf structure, including excavating, backfilling and providing utilities. Items include: deliver 1,075 port-purchased 24-inch concrete piling; supply and deliver 39,820 linear feet steel piling; supply and deliver 10,962 linear feet 16-inch square fender piling; supply and deliver 2,052 linear feet steel sheet piling; drive 912 24-inch hollow concrete piling; drive 163 24-inch solid concrete piling; drive 406 24-inch steel piling; and drive 2,052 linear feet steel sheet piling.

Address: 1815 Port of Tacoma Road, Tacoma

Original contract amount: $14,442,322

Start of construction: December 1997

Expected completion date: Nov. 30, 1998

Contractor: American Construction, 411 13th St., Everett, WA 98201, 425-259-0118

Owner: Port of Tacoma

Project participants: Rebar International and Associated Electric & Alarm.