[DJC]
# 19
[TOP]

Port of Edmonds Marina Reconstruction

Port of Edmonds Marina

Port of Edmonds Marina Reconstruction



Project description: Project was a direct result of a natural disaster that occurred last year. An emergency cleanup was conducted by Hurlen Construction. This project includes installation of steel piles, concrete float systems, and a concrete and steel bulkhead.

Project also includes structural steel frame work, roofing and utilities for the reconstruction of a small boat harbor. The project consists of approximately 370 steel piles, a 90,000-square-foot floating dock, 240,000 square feet of roofing for covered moorage, fire water, potable water, an electrical system, five gangways and miscellaneous site work for the gangway access.

Port of Edmonds Marina



Address: 336 Admiral Way, Edmonds

Original contract amount: $11,793,221

Start of construction: July 1997

Expected completion date: Dec. 15, 1998

Contractor: MKB Constructors, 3647 Stone Way N., Seattle, WA 98103-8065, 206-634-1700

Engineer: Peratovich, Nottingham & Drage Inc., 811 First Ave., Suite 260, Seattle, WA 98104, 206-624-1387

Owner: Port of Edmonds

Project participants: Gehri Sheet Metal; Jesse Engineering; Dalton Electric; Bellingham Marine; Makers Architectural and Urban Planning; Sparling Inc.; and McGowan Broz Engineers Inc.