homeWelcome, sign in or click here to subscribe.login
     


 

 

Construction


print  email to a friend  reprints add to mydjc  

October 2, 2015

Bertha's pit stop should be over by Thanksgiving

Photo from WSDOT [enlarge]

Don't blink — in a month Bertha will disappear and you won't likely see the tunneling machine again for another year.

The latest schedule from August shows crews from Seattle Tunnel Partners next week will take measurements of the machine's front body, cutterhead and seal gaps. Later this month they will test the center agitator, cutter equipment and other systems.

On Nov. 3, STP will begin backfilling the rescue pit to 4 feet above the machine's crown. A week later, crews will add more fill.

Systems will be tested again after the machine is covered with fill, then Bertha will resume tunneling on Nov. 23.

On Jan. 19, Bertha is expected to reach Safe Haven 3, the final stop before tunneling below the viaduct. It is scheduled to leave Safe Haven 3 on Feb. 12 after STP makes sure everything is in proper working order.

Bertha is expected to finish tunneling in late November next year. The schedule indicates the tunnel will open to traffic on March 9, 2018.

A spokeswoman for WSDOT said the schedule changes frequently and the agency can't verify any dates. An email inquiry to Chris Dixon, STP's project manager, wasn't immediately returned.

The tunnel opening is more than two years behind schedule.

Bertha broke down in December 2013 after overheating about 1,000 feet along its 9,270-foot route.




Email or user name:
Password:
 
Forgot password? Click here.