#6. McNeil Island Special Commitment Center

Total project cost: $55 million
(construction cost $44.8 million)

Project address:
McNeil Island

Start of construction:MAugust 2001

Expected completion date:
November 2003

Owner:
Washington State Department of Corrections


Description
McNeil Island Special Commitment Center includes a secured multilevel housing complex for 228 residents with an attached medical/dental support facility, a 12,500-square-foot secured entry/visiting building and a secured telecommunications building.

The project also includes an expansion of the current steam boiler and electrical plant, and a remodel of several existing support facilities for administration, food service/dining, recreation and the commissary.

A total of three new buildings will be constructed totaling 125,000 square feet. Another two buildings will be remodeled.

Additional work includes extensive site preparation and primary utility installations, demolition, security fencing & perimeter electronic surveillance, and paving/landscaping.

The project has extremely difficult site logistics because of its island location. Ferries and barges are being used to transport personnel, materials and equipment.

Because McNeil Island is essentially an island wildlife refuge that hosts corrections facilities on some portions, measures are being taken to prevent sediment run-off and contamination of any of the sensitive shoreline and wetlands areas during construction.

PROJECT PARTICIPANTS

GC/CM contractor:
Absher-Kitchell JV, P.O. Box 280, Puyallup, WA 98371, (253) 845-9544

Architect:
KMB Justice Facilities Group, 828 Seventh Ave. S.E., Olympia WA 98501, (360) 352-8883


Other Participants
Auburn Mechanical Inc.
Goodfellow Bros. Inc.
Potelco Inc.
Wagner Development Inc.