#14. Tacoma Link light rail segment

Original contract amount: $22.93 million

The light rail segment will run from downtown Tacoma to the Tacoma Dome Transit Center.
Map courtesy of Sound Transit

Project address:
Tacoma Dome Station to downtown Tacoma to Burlington over the Skagit River

Start of construction: July 9, 2001

Expected completion date:
Winter 2003

Owner:
Sound Transit


Description
The Tacoma Link light rail segment is a major part of Sound Transit’s regional transportation infrastructure project.

The 1.6-mile segment will run from the downtown area to the Tacoma Dome Transit Center and Freighthouse Square, and will connect regional bus routes with Amtrak and commuter trains at the Tacoma Dome Station.

Gary Merlino Construction is undertaking the work of building and installing embedded track, demolishing the 25th Street Bridge and reconstructing the vaulted sidewalks on East 25th Street. The project also includes large-scale infrastructure modifications to the city’s utilities, and relocation of a number of private utilities.

PROJECT PARTICIPANTS

Contractor:
Gary Merlino Construction, 9125 10th Ave. S., Seattle, WA 98108-4600, (206) 762-9125

Other Participants
Cascade Testing Labs
Coates Survey
Corrosion Mitigation
Railroad Emergency Services
Security Barricade
T. Yorozu Gardening
Totem Electric
Tucci and Sons
Unlimited Tile
Williams Manufacturing