Concrete Paving

West 27th Avenue intersection and Kennewick Avenue to State Route 182
Location: State Route 395 and Kennewick Avenue, Kennewick
Owner/Developer: Washington State Department of Transportation

Project Team:
Inland Asphalt (Acme Materials & Construction), general and concrete contractor;
and Central Pre-Mix Co., ready-mix supplier.


Less than a month was needed to rebuild three intersections in the city of Kennewick.
Photo courtesy of WSDOT

The project consisted of the full reconstruction of three intersections in the heart of Kennewick that had experienced shoving and rutting from the 26,800 vehicles that travel them each day.

Construction was performed on a fast-track schedule to address concerns from the city of Kennewick. The state Department of Transportation held meetings with the city and the contractor to develop a schedule that limited construction time to just a few days per intersection.

The plan included closing the intersections between 7 p.m. and 6 a.m. Thursdays through Mondays. The result was 4,800 cubic yards of concrete were placed from Sept. 10-Oct. 2 last year.