March 19, 2025
SEATTLE — King County is seeking industry feedback on construction plans ahead of soliciting the upcoming Mouth of Duwamish Combined Sewer Overflow project.
According to a request for information issued Tuesday , the county eventually plans to use the general contractor/construction manager delivery method for the treatment station estimated at $600 million to $2.3 billion. Responses to the RFI are due by 1:30 p.m. on April 8 to the county's E-Procurement Supplier Portal.
. . .