Seattle Center Central Utility Plant

special issues index

January 27, 2000


Alternative Bid Projects started in 1999
Seattle Center Central Utility Plant

Cost
$6.5 million

Address
305 Harrison St., Seattle

Start of construction

June 17, 1999

Expected completion date
May 31, 2000

Owner
Seattle Center

Pacific Tower renovation at the University of Washington.
The $6.5 million project is expected to be finished by the end of May.
Office and shop space is included in the project.
Photos by Laura Swimmer


Description
The new Central Utility Plant for the Seattle Center will have a footprint of about 10,000 square feet and will include office and shop spaces for the Center’s Building Operating Engineers.

Mechanical systems will include new chillers with a capacity of 3,500 tons and new boilers with about 1,750 horsepower capacity. Cooling tower capacity will be 3,500 tons.

PROJECT PARTICIPANTS
GC/CM contractor
Baugh Construction Co.
900 Poplar Place S., Seattle, WA 98114-0135
(206) 726-8000

Architect
LMN
501 Norton Building, 801 Second Ave., Suite 501, Seattle, WA 98104
(206) 682-3460

Subcontractors, Subconsultants & Suppliers
CDi Mechanical Engineers
The Greenbusch Group
Hurlen Construction
Carla Keel Group
University Mechanical
Haight Roofing
ECS Engineering
Mountain States
CTI
AKB Engineers
GBC Contractors
Deeny Construction
Davis Langdon Adamson
DBM
PCS

<< Previous project | Top 20 main page | Go to hard bid projects >>