Project description: Renovate 127,000-square-foot Bohler Gymnasium at Washington State University. The building was constructed in 1928. It contains the Athletic Department and gymnasium space as well as offices, locker rooms, showers and athletic support spaces. New structural work includes mini-piles, concrete shear walls and removing and reconstructing portions of the roof utilizing structural steel systems. The expanded exterior includes new brick, aluminum windows and roofing.
Original contract amount: $13,138,000.
Start of construction: October 1998.
Expected completion date: March 2000.
Contractor: Garco Construction, East 4114 Broadway, Spokane,WA 99202, (509) 535-4688.
Architect: Sasaki Associates, Inc., 900 N. Point St., Suite B300, San Francisco, CA 97109, (415) 776-7272
Owner: Washington State University.
Project participants:
C3 Management Group, Inc. Door + Hardware Consultants, Inc. Gifford Consulting Stewart Associates Creighton Engineering Elcon Associates, Inc. Sound Technology Consultants Thomas J. Gerard & Associates Summit Technology Advanced Insulation Co. Champion Concrete Pumping, Inc. Dupree Building Specialties Hayward Baker, Inc.
|
Advanced Terrazzo and Ceramics, Inc. Dew Drop Grinnell Fire Protection Heritage Electric Hobson Fabricating Corp King Brothers Woodworking, Inc. Modern Drywall, Inc. Performance Contracting, Inc. Sound Elevator Summit Window and Patio Door TLH Abatement, Inc. Yadon Construction Specialties, Inc. Johnson Western Gunite Co. Kruger Sheet Metal
|
Nor-Pac Systems, Inc. Poe Asphalt Paving, Inc. Spilker Masonry The
Won-Door Corp. Trecon, Inc. A.I.C. Material C & B Ready-Mix, Inc. Contractors Supply Flaig Steel and Fabricating, Inc. Yakima Steel Fabricators, Inc. Conover Concrete Drake Forest Products, Inc. Tombari Structural Products, Inc.
|
djc home | top | special issues index
|