Project 15 - Tumwater High School
Journal staff
|
Tumwater High School rendering.
|
Project description: Modernization of existing high school, including new mechanical and electrical systems, structural upgrades, a new roof structure and storm drainage system. Three buildings totaling 163,927 square feet will be remodeled for a new library, administration area, kitchen and updated performing arts center.
Address: 700 Israel Road, Tumwater.
Original contract amount: $14,349,562.
Start of construction: March 2, 1998.
Expected completion date: Aug. 31, 1999.
Contractor: Berschauer Phillips Construction Co. Inc., 700 Israel Road, Tumwater, WA 98101, (360) 754-5788.
Architect: The BJSS Group Architects and Planners, 300 W. Bay Drive, Suite 212, Olympia, WA 98502, (360) 943-4650.
Owner: Tumwater School District.
Project participants:
Sargent Engineers Inc. AHBL Hargis Engineers Inc. F.S. and G.S. Services Trepus Corp. DLB Earthworks Looker & Assoc. Inc. Landscaping Services Fence Specialists Addison Construction Supply Holroyd Co. Dunson Construction Western Superior Sessler Inc. Standard Structures Inc. Truss Components of Washington Glulam Resources Inc. Ritter Cabinet Manufacturing Insulpro Projects LLC Wayne's Roofing Inc.
|
J&M Roofing Northshore Sheet Metal Cascade Steel Door & Hardware Four T's Installation Larson's Glass Co. Pacific Wood Zesbaugh Inc. Lacey Glass NW Campbell Unlimited Tile Audio Acoustics Inc. Rubenstein's Contract Carpet Long Painting Nelson Adams W.H. Cress Co. Foley Sign Co. Casco Carbon Dioxide Inc. Lair-Swanson Foster-Bray Co.
|
Dorse Architectural Stagecraft Industries Global Hotel Supply Fuller & D'Albert Northwest School Equipment Fairway Mechanical Trinity Fire Protection Totem Electric Climate Engineers ATS Automation Hudson Bay Insulation Zephyr Communications Dimensional Communications TP Installation Ivy Hi Lift Hanset Stainless Eichler Backhoe & Construction Rincon American Pipe Lining Inc.
|
djc home | top | special issues index
|