Subscribe / Renew |
|
Contact Us |
|
► Subscribe to our Free Weekly Newsletter |
home | Welcome, sign in or click here to subscribe. | login |
print email to a friend reprints add to mydjc |
May 9, 2014
CAST-IN-PLACE PARKING STRUCTURES
Location: Suquamish
Owner/developer: Port Madison Enterprises (Suquamish Tribe)
Project team: Korsmo Construction, general contractor; Rice Fergus Miller, architect; Coughlin Porter Lundeen, structural engineer; Turnstone Construction, decorative concrete contractor; Conco, concrete contractor; Hard Rock, ready-mix supplier
The Suquamish Clearwater Casino Resort is undertaking a major five-year expansion, including a 700-space parking garage that was completed earlier this year.
The seven-level, 214,500-square-foot long-span structure is supported by post-tensioned beams. Shear walls are positioned around the perimeter.
Interior concrete surfaces have a swirl finish.
The exterior walls have sculpted shotcrete murals that express the tribe’s heritage and connection to the waterways of Puget Sound.
Other Stories: