homeWelcome, sign in or click here to subscribe.login
     


 

 

Construction


print  email to a friend  reprints add to mydjc  

May 2, 2013

Demolition

Photo courtesy of NCM Contracting Group [enlarge]
NCM performed extensive interior demolition and removed old facades and windows.

Edith Green-Wendell Wyatt Federal Building

NCM Contracting Group


General contractor: Howard S. Wright, a Balfour Beatty Co.

Engineer: Roggenkamp Structural Engineers

Owner: U.S. General Services Administration

The Edith Green-Wendell Wyatt Federal Building, named after two former U.S. Representatives from Oregon, was built in 1975 in Portland’s central business district. The 18-story building occupies one full city block and includes two levels of basement and parking areas.

When the U.S. General Services Administration was ready to renovate this facility, the agency’s commitment to sustainable federal workplaces was a crucial cornerstone of the project. Renovations funded by the American Recovery and Reinvestment Act were designed to achieve LEED platinum certification.

NCM performed the extensive interior demolition and abatement of hazardous materials, including asbestos and lead-based paint, as the first step in this green renovation. The demolition included all walls, floors, ceilings, and mechanical equipment and systems. Additional selective structural demolition supported the extension of the elevators’ tower crane and the extension of the slab for all floors.

NCM also removed old facades and window assemblies, two passenger elevators, one shuttle elevator, two stairways, planters, curbs, sidewalks and pavers.

The location of the project in the center of a busy downtown required greater focus on safety, equipment and hauling, as well as noise and dust mitigation.

NCM was one of seven first-tier subcontractors who were collocated in the federal building for seven months, collaborating on an integrated delivery approach. This collaborative strategy enabled NCM to develop the demolition and abatement drawings and specifications in concert with the schedules and resources of the other subcontractors, resulting in efficiencies and cost savings.

The finished high-performance green building is expected to cut the energy needed for lighting by 40 percent and water use by 65 percent, plus new elevators will actually generate power as they descend.

Because the Edith Green-Wendell Wyatt Building required extensive demolition and abatement of hazardous materials, including asbestos and lead-based paint, NCM did a complete site-specific safety plan in addition to its corporate safety plan and training. In the 56,511 hours worked on the project there were no medical-only injuries and only one time-loss injury.


Other Stories:



Email or user name:
Password:
 
Forgot password? Click here.